Boughrara Fishing Harbour
| |
GENERALINFORMATION
| Exploitation Date |
1986 |
| Extension |
--- |
| Geographical position |
33° 31' North et 10° 41' East |
| Governorate |
Medenine |
| Global Cost |
2 MD |
| Type |
Costal harbour |
INFRASTRUCTURE
| Dike |
440 m |
| Quay |
--- |
| Floating quay |
240 m of 2 m |
| Basins |
1,65 ha |
| Harbour public domain |
0,7 ha |
| Markers |
--- |
| Fences |
--- m |
| Network - Lighting |
17 Candelabras (01 01 transformer) |
| Projectors |
--- |
| Drinking water |
01 distributor |
| Electricity |
01 distributor |
| Network - Purification |
100 m |
| Extinction of fires Point |
--- |
SUPERSTRUCTURE
| hoist equipment |
01 Permanent crane of 01 T |
| Slip way |
--- |
| Ramendage space |
--- m² |
| Fish market space for
export |
--- m² |
| Fish market space under the levelling program |
168 m² |
| Diesel station |
01 with a capacity of 20 m 3 |
COLD FACILITIES
Designation |
Property |
| |
APIP |
Private |
Refrigerated complexes (Nbre) |
01 |
--- |
Storage capacity in T (0°C) |
08 |
--- |
| Storage capacity in T (-25°C) |
--- |
--- |
| Tunnel capacity (T/D) |
--- |
--- |
| Ice storage capacity in T |
20 |
--- |
| Ice production in (T/D) |
05 |
--- |
|
|
|
|